Which of the following is not true for action notices that are produced by MRP systems?


A) An action notice is produced when a planned order needs to be released.
B) An action notice is produced when due dates of orders need to be adjusted.
C) An action notice is produced when the lead time is not sufficient for a planned order.
D) An action notice is produced when inventory is moved to the manufacturing floor.
E) They indicate actions that need to be taken by inventory planners.

Correct Answer

verifed

verified

D

What is the primary objective of ERP?

Correct Answer

verifed

verified

Integrate all departments and ...

View Answer

For any period the beginning inventory, plus any replenishment order due, less the gross requirement equals planned orders.

Correct Answer

verifed

verified

ERP systems provide _____ and _____ benefits.


A) tangible, HR
B) intangible, marketing
C) marketing, operation
D) tangible, intangible
E) CEO, CFO

Correct Answer

verifed

verified

The three criteria for selecting an ERP system include _____________, ________________, and _______________.

Correct Answer

verifed

verified

functionality, ease ...

View Answer

The time interval necessary to either manufacture or purchase an item is its ______________.


A) time fence
B) lead time
C) safety time
D) time bucket
E) receipt time

Correct Answer

verifed

verified

Selection of the lot size rule to be used should be based on minimizing ____________________.


A) the order size
B) late shipments
C) total processing time
D) quality problems
E) the sum of ordering and carrying costs

Correct Answer

verifed

verified

___________________ uses the planned orders generated by MRP to evaluate the feasibility of long-term or blanket contracts and to determine delivery need.

Correct Answer

verifed

verified

Owens Corning reported savings of ______________ by using ERP.


A) $6 million
B) $16 million
C) $65 million
D) $600 million
E) $660 million

Correct Answer

verifed

verified

Given the following data: Given the following data:     The end product J is made from components K and L. The authorized MPS calls for 200 J to be completed in week 3, 300 J to be completed in week 5, and 300 J to be completed in week 6. There is a scheduled receipt of 400 L in week 2. (a) What are the gross requirements for K and L? (b) What are the planned orders for K and L? The end product J is made from components K and L. The authorized MPS calls for 200 J to be completed in week 3, 300 J to be completed in week 5, and 300 J to be completed in week 6. There is a scheduled receipt of 400 L in week 2. (a) What are the gross requirements for K and L? (b) What are the planned orders for K and L?

Correct Answer

verifed

verified

(a) for K - 1,600 in week 2, 2,400 in we...

View Answer

The current time period is referred to as __________________.


A) time zero
B) the point of departure
C) the start time
D) the action bucket
E) this year

Correct Answer

verifed

verified

With capacity requirements planning, the calculated workload for a work center is compared with ___________.


A) available capacity
B) calculated workloads for other work centers
C) the cost of expanding the work center
D) standard capacity
E) design capacity

Correct Answer

verifed

verified

A

If an order is not scheduled to arrive in time, the planner tries to cancel the order.

Correct Answer

verifed

verified

A computer-based information system designed to manage dependent demand inventory is _____________.


A) manufacturing resources planning
B) multifunctional requirements planning
C) material relationships planning
D) material requirements planning
E) manufacturing requirements planning

Correct Answer

verifed

verified

Given the following data: Given the following data:     (a) What are the workloads for periods 3 and 4? (b) There are 168 hours of operating time per machine each period. How many machines should be operated for periods 3 and 4? (a) What are the workloads for periods 3 and 4? (b) There are 168 hours of operating time per machine each period. How many machines should be operated for periods 3 and 4?

Correct Answer

verifed

verified

(a) 416.2 hours for period 3, and 1,197.7 hours for period 4; (b) 3 machines for period 3, and 8 machines for period 4

Which of the following is not true for planned orders?


A) They are necessary only for finished products.
B) They result when there is not enough inventory to cover the gross requirements.
C) The quantity is calculated using the lot-sizing rule.
D) The lead time is required to determine when the order should be placed.
E) The inventory records file is updated for the order.

Correct Answer

verifed

verified

Which of the following most closely describes dependent demand?


A) demand generated by suppliers
B) demand that is seasonal
C) demand estimates using regression analysis
D) demand derived from finished products
E) demand for repair parts

Correct Answer

verifed

verified

The primary objective of ERP is to integrate all departments and functions, internal and external, onto a single computer system to serve the enterprise's needs.

Correct Answer

verifed

verified

Supply chain intelligence enables ______________ along the supply chain.

Correct Answer

verifed

verified

strategic ...

View Answer

A(n) __________ sets up and runs ERP systems.

Correct Answer

verifed

verified

Applicatio...

View Answer

Showing 1 - 20 of 137