Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) less than or equal to 0.5 days
B) greater than 0.5 but less than or equal to 1.0 day
C) greater than 1.0 but less than or equal to 1.5 days
D) greater than 1.5 days
Correct Answer
verified
Multiple Choice
A) Activities A and B.
B) Activities E and A.
C) Activities A and C.
D) Activities B and D.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Define
B) Organize
C) Improve
D) Close
Correct Answer
verified
Multiple Choice
A) the number and definition of each project activity.
B) the normal time to complete each activity.
C) the immediate predecessors (i.e., the precedent relationships) .
D) the probabilities of completing each activity.
Correct Answer
verified
Multiple Choice
A) The expected time is given and not computed using formulas.
B) The probability of completing the project on time is 0 when the project target completion time equals the expected time.
C) The normal probability distribution is not used in PERT methods.
D) The variance in project duration is given by the sum of the variances of the critical path activities.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) less than 4.
B) between 4 and 6.
C) between 6 and 8.
D) greater than 8.
Correct Answer
verified
Multiple Choice
A) The activity time estimates are accurate and stable.
B) Activities are dependent on each other.
C) Activities can be interrupted before completion.
D) The project schedule defines a correct sequence of work in terms of technology and workflow.
Correct Answer
verified
Multiple Choice
A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) Activity A
B) Activity B
C) Activity C
D) Activity D
Correct Answer
verified
Multiple Choice
A) Less than or equal to 2 days
B) Greater than 2 but less than or equal to 4 days
C) Greater than 4 but less than or equal to 6 days
D) Greater than 6 days
Correct Answer
verified
Multiple Choice
A) The activities on the critical path take the shortest time to complete.
B) The activities on the critical path define the total project completion time.
C) It is the project path with zero slack.
D) The delays in critical path activities will delay the project.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) A-D-E; 17 weeks
B) A-C-E; 16 weeks
C) B-E; 14 weeks
D) A-D-E; 18 weeks
Correct Answer
verified
Showing 61 - 80 of 108