Explain the stages of the project life cycle and what types of decisions are normally made at each stage.

Correct Answer

verifed

verified

The following are the stages of the proj...

View Answer

The Critical Path Method (CPM) allows for an evaluation of uncertainty in project completion times.

Correct Answer

verifed

verified

A statement of work would be developed in the "organize" step of the project life cycle.

Correct Answer

verifed

verified

A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:  Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions -The expected variance of Activity A is _____.


A) less than or equal to 0.5 days
B) greater than 0.5 but less than or equal to 1.0 day
C) greater than 1.0 but less than or equal to 1.5 days
D) greater than 1.5 days

Correct Answer

verifed

verified

Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!  Activity  Immediate  Predecessor(s)   Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array} -The most likely activities to share resources with critical path activities are:


A) Activities A and B.
B) Activities E and A.
C) Activities A and C.
D) Activities B and D.

Correct Answer

verifed

verified

Strong leadership is an impediment to project management success because of the team-based nature of most projects.

Correct Answer

verifed

verified

Which of the following is NOT a stage in the project life cycle?


A) Define
B) Organize
C) Improve
D) Close

Correct Answer

verifed

verified

The critical path method (CPM) work breakdown structure consists of all of the following EXCEPT:


A) the number and definition of each project activity.
B) the normal time to complete each activity.
C) the immediate predecessors (i.e., the precedent relationships) .
D) the probabilities of completing each activity.

Correct Answer

verifed

verified

Which one of the following statements about Project Evaluation and Review Technique (PERT) is TRUE?


A) The expected time is given and not computed using formulas.
B) The probability of completing the project on time is 0 when the project target completion time equals the expected time.
C) The normal probability distribution is not used in PERT methods.
D) The variance in project duration is given by the sum of the variances of the critical path activities.

Correct Answer

verifed

verified

You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks).  Likely  Project Immediate Optimistic  Most Pessimistic Expected tActivity  Activity Predecessor(s) Time Time  Time  Time  Variance  A  none 251464 B  none 81114111 C  A 57970.44 D  A 691291 E  B. C D 13530.44\begin{array}{lcrrrrc}&&&\text { Likely }\\\text { Project}&\text { Immediate }&\text {Optimistic }&\text { Most }&\text {Pessimistic }&\text {Expected t}&\text {Activity }\\\text { Activity}&\text { Predecessor(s) }&\text {Time}&\text { Time }&\text { Time }&\text { Time }&\text { Variance }\\\hline\text { A } & \text { none } & 2 & 5 & 14 & 6 & 4 \\\text { B } & \text { none } & 8 & 11 & 14 & 11 & 1 \\\text { C } & \text { A } & 5 & 7 & 9 & 7 & 0.44 \\\text { D } & \text { A } & 6 & 9 & 12 & 9 & 1 \\\text { E } & \text { B. C D } & 1 & 3 & 5 & 3 & 0.44\end{array} a.What is the critical path and expected completion time for this project? b.Which activity has the largest slack, and how large is that slack? c.What is the probability that the project will be completed within 16 weeks? d.If the expected time (not the most likely time) for activity B is changed to 18 weeks from 11 weeks, by how many weeks will the project's expected completion time increase?

Correct Answer

verifed

verified

a.A-D-E; 18 weeks
b....

View Answer

Using a beta probability distribution to characterize uncertain activity times is practical because it allows managers to use judgmental estimates to identify the distribution.

Correct Answer

verifed

verified

Consider the following project network. Time estimates are in weeks.  Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | }  \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}  -Slack for activity E is: A)  less than 4. B)  between 4 and 6. C)  between 6 and 8. D)  greater than 8. Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array} -Slack for activity E is:


A) less than 4.
B) between 4 and 6.
C) between 6 and 8.
D) greater than 8.

Correct Answer

verifed

verified

Which one of the following statements about the critical path method (CPM) is TRUE?


A) The activity time estimates are accurate and stable.
B) Activities are dependent on each other.
C) Activities can be interrupted before completion.
D) The project schedule defines a correct sequence of work in terms of technology and workflow.

Correct Answer

verifed

verified

Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!  Activity  Immediate  Predecessor(s)   Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES -The largest amount of slack that any activity has in this project is:


A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.

Correct Answer

verifed

verified

Consider the project network and data shown below:  Consider the project network and data shown below:    \begin{array}{|c|c|c|c|c|c|} \hline\text { Activity } & \begin{array}{c} \text { Normal Time } \\ \text { (Months) } \end{array} & \begin{array}{c} \text { Crash Time } \\ \text { (Months) } \end{array} & \begin{array}{c} \text { Normal } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Cost/Month } \end{array} \\ \hline \text { A } & 3 & 2 & \$ 100,000 & \$ 150,000 & \\\hline \mathrm{B} & 6 & 4 & \$ 200,000 & \$ 320,000 \\ \hline \mathrm{C} & 2 & 2 & \$ 90,000 & \$ 90,000 \\ \hline \mathrm{D} & 2 & 1 & \$ 180,000 & \$ 250,000 \\ \hline \mathrm{E} & 4 & 2 & \$ 225,000 & \$ 450,000 \\ \hline \mathrm{F} & 7 & 6 & \$ 80,000 & \$ 120,000 \\ \hline \mathrm{G} & 4 & 2 & \$ 310,000 & \$ 500,000 \\ \hline \mathrm{H} & 2 & 2 & \$ 400,000 & \$ 400,000 \\ \hline \end{array}   a.Determine the critical path. b.If management wants the project done in one less month, which activity should they crash?  Activity  Normal Time  (Months)  Crash Time  (Months)  Normal  Cost  Crash  Cost  Crash  Cost/Month  A 32$100,000$150,000B64$200,000$320,000C22$90,000$90,000D21$180,000$250,000E42$225,000$450,000F76$80,000$120,000G42$310,000$500,000H22$400,000$400,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Normal Time } \\\text { (Months) }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { (Months) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash } \\\text { Cost/Month }\end{array} \\\hline \text { A } & 3 & 2 & \$ 100,000 & \$ 150,000 & \\\hline \mathrm{B} & 6 & 4 & \$ 200,000 & \$ 320,000 \\\hline \mathrm{C} & 2 & 2 & \$ 90,000 & \$ 90,000 \\\hline \mathrm{D} & 2 & 1 & \$ 180,000 & \$ 250,000 \\\hline \mathrm{E} & 4 & 2 & \$ 225,000 & \$ 450,000 \\\hline \mathrm{F} & 7 & 6 & \$ 80,000 & \$ 120,000 \\\hline \mathrm{G} & 4 & 2 & \$ 310,000 & \$ 500,000 \\\hline \mathrm{H} & 2 & 2 & \$ 400,000 & \$ 400,000 \\\hline\end{array} a.Determine the critical path. b.If management wants the project done in one less month, which activity should they crash?

Correct Answer

verifed

verified

You are responsible for managing an advertising project with the following activities (times are given in weeks) .  Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)   (Weeks)   Cost ($)  Cost ($)  A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$) \\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES -Which of the following activities has the largest amount of slack?


A) Activity A
B) Activity B
C) Activity C
D) Activity D

Correct Answer

verifed

verified

A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:  Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions -The expected duration of Activity A is _____.


A) Less than or equal to 2 days
B) Greater than 2 but less than or equal to 4 days
C) Greater than 4 but less than or equal to 6 days
D) Greater than 6 days

Correct Answer

verifed

verified

Which is NOT true of the critical path?


A) The activities on the critical path take the shortest time to complete.
B) The activities on the critical path define the total project completion time.
C) It is the project path with zero slack.
D) The delays in critical path activities will delay the project.

Correct Answer

verifed

verified

Explain the purpose of Gantt charts.

Correct Answer

verifed

verified

Gantt charts enable the project manager ...

View Answer

Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks) .  Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)   Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES  PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }  Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array} -Using the table for the advertising and promotion project, what is the critical path and expected completion time for this project?


A) A-D-E; 17 weeks
B) A-C-E; 16 weeks
C) B-E; 14 weeks
D) A-D-E; 18 weeks

Correct Answer

verifed

verified