Filters
Question type

Study Flashcards

What are the four steps in the effective management of variance analysis?

Correct Answer

verifed

verified

The four steps are: (1) prepar...

View Answer

Briefly describe the procedure of management by exception.

Correct Answer

verifed

verified

Management by exception is an analytical...

View Answer

Regarding overhead costs, as volume increases:


A) Total variable cost decreases, total fixed cost remains constant.
B) Both total fixed cost and total variable cost increase.
C) Total fixed cost increases, total variable cost remains constant.
D) Total fixed cost remains constant, total variable cost increases.
E) Both total fixed cost and total variable cost remain constant.

Correct Answer

verifed

verified

A company provided the following direct materials cost information. Compute the direct materials price variance. Standard costs assigned:\text {Standard costs assigned:} Direct materials standard cost (405,000 units @$2.00/unit)  $810,000 Actual costs:Direct Materials costs incurred ( 403,750 units@$2.20/unit)  $888,250\begin{array}{llr} \text {Direct materials standard cost (405,000 units @\$2.00/unit) } & \$ 810,000\\ \text { Actual costs:} &\\ \text {Direct Materials costs incurred ( 403,750 units@\$2.20/unit) } &\$ 888,250 \end{array}


A) $81,000 Unfavorable.
B) $80,750 Favorable.
C) $78,250 Favorable.
D) $80,750 Unfavorable.
E) $81,000 Favorable.

Correct Answer

verifed

verified

What are some causes of direct labor rate and efficiency variances?

Correct Answer

verifed

verified

The use of workers with different skill ...

View Answer

Match the following definitions with the appropriate term

Premises
Occurs when there is a difference between the actual and standard volume of production.
A planning budget based on a single predicted amount of sales or other activity measure.
Preset costs for delivering a product, or service under normal conditions.
A process of examining differences between actual and budgeted sales or costs and describing them in terms of the price and quantity differences.
The difference between actual price per unit of input and standard price per unit of input.
A budget prepared based on several different amounts of sales, often including a best-case and worst-case scenario.
The difference between actual quantity of input used and standard quantity of input used.
The difference between actual overhead costs incurred and the budgeted overhead costs based on a flexible budget.
A management process to focus on significant variances and give less attention to areas where performance is close to the standard.
The difference between actual and standard cost.
Responses
Cost variance
Volume variance
Price variance
Quantity variance
Standard costs
Controllable variance
Fixed budget
Flexible budget
Variance analysis
Management by exception

Correct Answer

Occurs when there is a difference between the actual and standard volume of production.
A planning budget based on a single predicted amount of sales or other activity measure.
Preset costs for delivering a product, or service under normal conditions.
A process of examining differences between actual and budgeted sales or costs and describing them in terms of the price and quantity differences.
The difference between actual price per unit of input and standard price per unit of input.
A budget prepared based on several different amounts of sales, often including a best-case and worst-case scenario.
The difference between actual quantity of input used and standard quantity of input used.
The difference between actual overhead costs incurred and the budgeted overhead costs based on a flexible budget.
A management process to focus on significant variances and give less attention to areas where performance is close to the standard.
The difference between actual and standard cost.

What are sales variances? How are they used?

Correct Answer

verifed

verified

Sales variances reflect differences in p...

View Answer

The following company information is available. The direct materials quantity variance is: Direct materials used for production 36,000 gallons Standard quantity for units produced 34,400 gallons Standard cost per gallon of direct material $ 6.00 Actual cost per gallon of direct material $ 6.10


A) $13,200 favorable.
B) $10,000 unfavorable.
C) $10,000 favorable.
D) $13,200 unfavorable.
E) $9,600 unfavorable.

Correct Answer

verifed

verified

Claymore Corp. has the following information about its standards and production activity for September. The volume variance is:  Actual total factory overhead incured $28,175Standard factory overhead:  Variable overhead $3.10 per unit produced  Fixed overhead  $ 12,000 / 6,000 estimated units to be produced $2per unit Actual units produced 4,800 units\begin{array}{lll} \text { Actual total factory overhead incured } &\$28,175\\ \text {Standard factory overhead: } &\\ \text { Variable overhead } &\$3.10&\text { per unit produced }\\ \text { Fixed overhead } &\\ \text { \$ 12,000 / 6,000 estimated units to be produced } &\$2&\text {per unit}\\ \text { Actual units produced } &4,800&\text { units}\\\end{array}


A) $2,400F.
B) $3,695U.
C) $1,295U.
D) $1,295F.
E) $2,400U.

Correct Answer

verifed

verified

While companies strive to achieve ideal standards, reality implies that some loss of materials usually occurs with any process.

Correct Answer

verifed

verified

Gala Enterprises reports the following information regarding the production on one of its products for the month. Compute the direct labor cost variance, the direct labor rate variance, the direct labor efficiency variance and identify each as either favorable or unfavorable.  Direct labor standard (2 hrs. @ $15/hr.)$30 per finished unit  Actual direct labor hours 60,800hrs. Actual finished units produced 30,000 units  Actual cost of direct labor $905,920\begin{array} { l l } \text { Direct labor standard (2 hrs. @ } \$ 15 / \mathrm { hr } . ) & \$ 30 \text { per finished unit } \\\text { Actual direct labor hours } & 60,800 \mathrm { hrs } . \\\text { Actual finished units produced } & 30,000 \text { units } \\\text { Actual cost of direct labor } & \$ 905,920\end{array}

Correct Answer

verifed

verified

Direct labor cost variance:
Actual units...

View Answer

A ______________contains relevant information that compares actual results to planned activities.

Correct Answer

verifed

verified

________ are preset costs for delivering a product or service under normal conditions.

Correct Answer

verifed

verified

The following information comes from the records of Magno Co. for the current period. a. Compute the overhead controllable and volume variances. In each case, state whether the variance is favorable or unfavorable. b. Prepare the journal entries to charge overhead costs to work in process and the overhead variances to their proper accounts.  Actual costs and quantities:  Direct materials used38,000 feet @ $6.20 per foot  Direct labor hours used 50,660 hours  Direct labor rate per hour $16 Factory overhead $211,60025,000 units were produced during the period. \begin{array}{ll}\text { Actual costs and quantities: }\\ \text { Direct materials used} & 38,000 \text { feet @ } \$ 6.20 \text { per foot } \\ \text { Direct labor hours used } & 50,660 \text { hours } \\ \text { Direct labor rate per hour } & \$ 16 \\\text { Factory overhead } & \$ 211,600 \\25,000 \text { units were produced during the period. }\end{array}  Standard costs and quantities per unit: \text { Standard costs and quantities per unit: }  Direct materials 1.5 ft. @ $6.10 per ft.Direct labor 2 hours@$17per hour\begin{array}{llr} \text { Direct materials } &\text {1.5 ft. @ \$6.10 per ft.}\\ \text {Direct labor } &\text {2 hours@\$17per hour}\\\end{array} Factory overhead (based on budgeted production of 24,500 units) Variable overhead $2.25 \$ 2.25 /direct labor hour Fixed overhead $1.95/ \$ 1.95 / direct labor hour

Correct Answer

verifed

verified

None...

View Answer

A flexible budget performance report compares the differences between:


A) Budgeted performance over several periods.
B) Actual performance over several periods.
C) Actual performance and standard costs at the budgeted sales volume.
D) Actual performance and budgeted performance based on actual sales volume.
E) Actual performance and budgeted performance based on budgeted sales volume.

Correct Answer

verifed

verified

Job #411 was budgeted to require 3.5 hours of labor at $11.00 per hour. However, it was completed in 3 hours by a person who worked for $14.00 per hour. What is the total labor cost variance for Job #4115?

Correct Answer

verifed

verified

None...

View Answer

A flexible budget is also called a ________ budget.

Correct Answer

verifed

verified

Identify and explain the primary differences between fixed and flexible budgets.

Correct Answer

verifed

verified

A fixed budget is prepared before an ope...

View Answer

Georgia, Inc. has collected the following data on one of its products. The direct materials price variance is: Direct materials standard (4 lbs. @ $1/lb.) $ 4 per finished unit Total direct materials cost variance-unfavorable $ 13,750 Actual direct materials used 150,000 lbs. Actual finished units produced 30,000 units


A) $16,250 unfavorable.
B) $16,250 favorable.
C) $30,000 unfavorable.
D) $33,000 favorable.
E) $13,750 unfavorable.

Correct Answer

verifed

verified

Product A has a sales price of $10 per unit. Based on a 10,000-unit production level, the variable costs are $6 per unit and the fixed costs are $3 per unit. Using a flexible budget for 12,500 units, what is the budgeted operating income from Product A?


A) $35,000.
B) $30,000.
C) $25,000.
D) $12,500.
E) $20,000.

Correct Answer

verifed

verified

Showing 201 - 220 of 223

Related Exams

Show Answer