Filters
Question type

Study Flashcards

The backward pass determines project duration.

Correct Answer

verifed

verified

Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon.

Correct Answer

verifed

verified

Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag?


A) Start to Start lags
B) Start to Finish lags
C) Finish to Finish lags
D) Finish to Start lags
E) Any of these could be correct.

Correct Answer

verifed

verified

In a project network, recycling through a set of activities or __________ is not permitted.

Correct Answer

verifed

verified

looping
Explanation: Looping i...

View Answer

Activities that can occur while an activity is taking place are called ________ activities.

Correct Answer

verifed

verified

parallel or concurrent
Explana...

View Answer

The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations.When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called


A) Hammock activities.
B) Concurrent engineering.
C) A forward pass.
D) Dissecting.
E) Laddering.

Correct Answer

verifed

verified

________ activities are to be completed immediately following a particular activity.


A) Merge
B) Burst
C) Predecessor
D) Successor
E) Parallel

Correct Answer

verifed

verified

When creating a project network, your primary input will be the


A) Project Charter.
B) Work Packages.
C) Risk Plan.
D) Communication Plan.

Correct Answer

verifed

verified

The backward pass in project network calculations determines all of the following EXCEPT


A) Latest time an activity can begin.
B) Earliest time an activity can finish.
C) The critical path.
D) How long an activity can be delayed.
E) Latest time an activity can finish.

Correct Answer

verifed

verified

The likelihood the original critical path(s) will change once the project is initiated is referred to as


A) Flexibility.
B) Resilience.
C) Sensitivity.
D) Concurrent engineering.
E) Rigidity.

Correct Answer

verifed

verified

An element in the project that consumes time is a(n)___________.

Correct Answer

verifed

verified

activity
Explanation: An activ...

View Answer

A network has only one critical path and the slack for noncritical activities is high.This network would appear to have a _______ level of sensitivity.

Correct Answer

verifed

verified

low
Explanation: Network sensitivity is ...

View Answer

Tom is responsible for ordering hardware for a custom home his company is building.The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days.Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer.He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days.Tom and the installer share 10 days of


A) Free Slack.
B) Shared Slack.
C) Total Slack.
D) Critical Slack.
E) Functional Slack.

Correct Answer

verifed

verified

Which of the following does NOT help describe a project network?


A) A graphic display of the flow and sequence of work through the project
B) Provides the basis for scheduling labor and equipment
C) Gives the times when activities can start and finish and when they can be delayed
D) Highlights major deliverables and identifies their completion dates
E) Identifies critical activities

Correct Answer

verifed

verified

A merge activity is one that merges with other activities into a succeeding activity.

Correct Answer

verifed

verified

A(n)________ activity has more than one successor activity.

Correct Answer

verifed

verified

burst
Explanation: Burst activ...

View Answer

It is acceptable for arrows to cross one another in a network diagram.

Correct Answer

verifed

verified

An activity that has more than one predecessor is a _________ activity.

Correct Answer

verifed

verified

merge
Explanation: A merge act...

View Answer

In a project network, ________ indicate activity dependency and project flow.

Correct Answer

verifed

verified

arrows
Explanation: The wide availabilit...

View Answer

A _________ activity is one that has more than one activity immediately preceding it.


A) Burst
B) Merge
C) Parallel
D) None of these choices are correct.

Correct Answer

verifed

verified

Showing 41 - 60 of 105

Related Exams

Show Answer