Filters
Question type

Study Flashcards

In order to shorten the duration of a project the project manager should limit the choices of activities to just those which are on the __________.

Correct Answer

verifed

verified

critical path
Explanation: After the cra...

View Answer

Cost slope can be determined by dividing the


A) Run by the rise.
B) Rise by the run.
C) Crash cost by the normal cost.
D) Normal cost by the crash cost.
E) Indirect cost by direct cost.

Correct Answer

verifed

verified

Overhead costs such as supervision, administration, consultants, and interest are examples of ________ project costs.

Correct Answer

verifed

verified

indirect
Explanation: Indirect costs gen...

View Answer

According to Brooks' Law, adding more people to a late project is most likely to have which of the following impacts?


A) Keep the project from slipping any further
B) Get the project back on schedule
C) Make the project slip further
D) Lead to burnout
E) Decrease team motivation

Correct Answer

verifed

verified

Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.


A) Labor
B) Direct
C) Project
D) Overhead
E) Interest

Correct Answer

verifed

verified

When crashing an activity, you always crash to its crash point.

Correct Answer

verifed

verified

Showing 101 - 106 of 106

Related Exams

Show Answer