Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Rectangle
B) Arrow
C) Inverted triangle
D) Diamond
E) A dashed line
Correct Answer
verified
Multiple Choice
A) Cycle time/Process time
B) Throughput time/Process velocity
C) Process velocity/Throughput time
D) Inventory/Throughput rate
E) Value-added time/Process velocity
Correct Answer
verified
Multiple Choice
A) Blocking
B) Buffering
C) Starving
D) Buffer
E) Setup time
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Rectangle
B) Arrow
C) Inverted triangle
D) Diamond
E) A dashed line
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Average time between completions of successive units
B) Ratio of the time a resource is activated over its use
C) Can be no more that 60 minutes
D) The same as utilization
E) The labor content of the item being measured
Correct Answer
verified
Multiple Choice
A) It features rapid delivery of a standard product.
B) All units of output are unique.
C) It responds directly to customer orders.
D) It allows the firm to avoid inventory costs.
E) It combines the best features of other processes.
Correct Answer
verified
Multiple Choice
A) Outsource activities.
B) Change the sequence of activities.
C) Improve teamwork.
D) Reduce management interference.
E) Introduce incentive pay
Correct Answer
verified
Multiple Choice
A) Process time/Cycle time
B) Throughput rate × Flow time
C) Process velocity/Flow time
D) Set up time/Throughput rate
E) Value-added time/Process velocity
Correct Answer
verified
True/False
Correct Answer
verified
Showing 41 - 57 of 57