When only one person is responsible for performing several activities, all due at the same time, this is an example of a(n) ________ constraint.


A) equipment
B) materials
C) technical
D) resource
E) logical

Correct Answer

verifed

verified

Resource leveling or smoothing can have all the following results on a project EXCEPT


A) lower peak resource demand.
B) reduced resource need over the life of the project.
C) reduced fluctuations in resource demand.
D) a longer project duration.
E) a more sensitive network.

Correct Answer

verifed

verified

A project scheduler is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, the scheduler would need 5 contractors in order for the activities to be completed on time. There are only 3 available for the project. This is an example of what type of constraint?


A) Technical
B) People
C) Equipment
D) Physical
E) Materials

Correct Answer

verifed

verified

Identify and briefly describe two ways to classify projects with scheduling problems.

Correct Answer

verifed

verified

Resource-constrained...

View Answer

Identify and give an example of the three types of resource constraints.

Correct Answer

verifed

verified

Equipment-...

View Answer

The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.

Correct Answer

verifed

verified

When scheduling activities in a resource-constrained project, typically the activity scheduled first has the __________ amount of slack.


A) least
B) most
C) greatest
D) maximum
E) modest

Correct Answer

verifed

verified

When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called _________.


A) prioritizing
B) preempting
C) overriding
D) splitting
E) All of these alternatives are correct.

Correct Answer

verifed

verified

When classifying projects, ________ constrained means that the amount of a specific resource is fixed and the duration of the project is flexible.


A) time
B) people
C) material
D) resource
E) equipment

Correct Answer

verifed

verified

A special truck that is needed on the project has been assigned to another project. This is an example of what type of resource constraint?


A) Working capital
B) People
C) Equipment
D) Information
E) Materials

Correct Answer

verifed

verified

A project manager has two engineers assigned to the project and does not have access to more even if the result means extending the completion date on the project. The project manager is managing a(n) ________.


A) time-constrained project
B) people-constrained project
C) engineer-constrained project
D) resource-constrained project
E) human-constrained project

Correct Answer

verifed

verified

This is used to compare the cost accounts between organizational units and deliverables.


A) Chart of Accounts
B) Earned Value
C) Project Schedule
D) Direct Labor Budget Rollup
E) Comparison Audit

Correct Answer

verifed

verified

The shortage of memory chips to produce a printed circuit motherboard is an example of a(n) ________ type of resource constraint.


A) physical
B) people
C) material
D) equipment
E) budget

Correct Answer

verifed

verified

If your project has spent $75,000 versus a budget of $70,000 and it is a week ahead of schedule, is it a certainty that your project is doing well? Explain why or why not.

Correct Answer

verifed

verified

Not necessarily. You need more...

View Answer

All of the following are types of resource constraints EXCEPT


A) materials.
B) people.
C) equipment.
D) information.
E) human.

Correct Answer

verifed

verified

Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?


A) Resources have been assigned to each activity so they are adequate to complete the project on time.
B) Technical dependencies between activities are known.
C) The project completion date can be established.
D) The project is ready to be implemented.
E) All of these are true statements once technical constraints have been established.

Correct Answer

verifed

verified

A project scheduler is trying to reallocate resources in a time-constrained project to create smoother resource utilization. The scheduler should first identify activities with the


A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.

Correct Answer

verifed

verified

If resources are not adequate to meet peak demands, the resulting reschedule is termed


A) resource-constrained scheduling.
B) time-constrained scheduling.
C) mandatory leveling.
D) project resource adjustment.
E) allocation.

Correct Answer

verifed

verified

If it becomes necessary to delay one or several late starts to accommodate resource limitations, this is called:


A) Resource scheduling
B) Resource smoothing
C) Resource-constrained scheduling
D) Splitting
E) Resource accommodation

Correct Answer

verifed

verified

A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.


A) predecessor
B) technical or logic
C) successor
D) serial
E) hard

Correct Answer

verifed

verified