Filters
Question type

Study Flashcards

Pacing in production processes refers to the fixed timing of the movement of items through the process.

Correct Answer

verifed

verified

Blocking in production processes is when activities in a stage must continue because there is no place to deposit completed items.

Correct Answer

verifed

verified

A bottleneck occurs when a stage in a production process is starving.

Correct Answer

verifed

verified

To reduce process flow time, you might try which of the following actions?


A) Perform activities in parallel.
B) Change the sequence of activities.
C) Reduce interruptions.
D) Acquire additional equipment.
E) All of these choices are correct.

Correct Answer

verifed

verified

When a make-to-order production process is used, production is based on forecasts.

Correct Answer

verifed

verified

Run time is calculated by multiplying the number of units in a batch by the setup time.

Correct Answer

verifed

verified

False

Which of the following best describes the term "cycle time"?


A) Average time between completions of successive units
B) Ratio of the time a resource is activated over its use
C) Can be no more that 60 minutes
D) The same as utilization
E) The labor content of the item being measured

Correct Answer

verifed

verified

A

Buffering in a production process refers to a storage area between stages of production activity where output of a stage is placed prior to being used in a "downstream" stage.

Correct Answer

verifed

verified

A rectangle is conventionally used in a process flowchart to represent a task or operation.

Correct Answer

verifed

verified

Utilization of a production process is the ratio of time that a resource is actually being used relative to the time it is available for use.

Correct Answer

verifed

verified

A process has three stages. Their capacities per hour are 45, 25, and 35 respectively. Due to its higher capacity, the first stage is the bottleneck.

Correct Answer

verifed

verified

A triangle is conventionally used in a process flowchart to represent a storage area or queue.

Correct Answer

verifed

verified

The operation time is the sum of the setup time, run time, and transfer time for a batch of parts that are run on a machine.

Correct Answer

verifed

verified

A job is said to be enlarged vertically if the worker performs a greater number or variety of tasks.

Correct Answer

verifed

verified

Consider a three sequentially stepped process named as Process A, Process B, and Process C. Input comes into Process A. Output from A goes into Process B. Output from B goes into Process C. Output of C is the final output. Suppose that it takes 2 minutes per unit in Process A, 3 minutes per unit in Process B and 1 minute per unit in Process C. Suppose further that Process A receives input at the rate of 30 per hour. Where would you place a buffer?


A) in front of Process A
B) in front of Process B
C) in front of Process C
D) in front of both Process B and Process C
E) None of these choices are correct.

Correct Answer

verifed

verified

Make-to-order production processes are well suited for high-volume production of a standardized product.

Correct Answer

verifed

verified

A process flowchart uses which of the following symbols to represent tasks or operations in a flow diagram?


A) Rectangle
B) Arrow
C) Inverted triangle
D) Diamond
E) A dashed line

Correct Answer

verifed

verified

Inventory turn is a better measure than the total value of inventory for comparative purposes because it is a relative measure.

Correct Answer

verifed

verified

Efficiency of a production process is the ratio of the actual output of a process to some standard.

Correct Answer

verifed

verified

Benchmarking refers to the practice of comparing the production metrics of one firm with the production metrics of another.

Correct Answer

verifed

verified

True

Showing 1 - 20 of 67

Related Exams

Show Answer