In a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)chart,each rectangular box,called a task box,has five sections that contain important information about a task.

Correct Answer

verifed

verified

The task duration is the same as the elapsed time.

Correct Answer

verifed

verified

Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)and Gantt charts are mutually exclusive techniques.

Correct Answer

verifed

verified

If any task along a critical path falls behind schedule,the entire project will be delayed.

Correct Answer

verifed

verified

A _____ displays the same information as the Gantt chart,including task dependencies,but uses task boxes to include much more detail.


A) semantic wireframe
B) mesh topology
C) ring topology
D) network diagram

Correct Answer

verifed

verified

Often,two or more concurrent tasks depend on a single prior task,which is called a _____.


A) predecessor task
B) wireframe task
C) beneficiary task
D) discrete task

Correct Answer

verifed

verified

If team members lack experience with certain aspects of the required technology,temporary help might be obtained from IT consultants or part-time staff.

Correct Answer

verifed

verified

A _____ is a proactive effort to anticipate a risk and describe an action plan to deal with it.


A) risk identification plan
B) risk response plan
C) risk balance plan
D) risk management plan

Correct Answer

verifed

verified

Effective project reporting requires _____.


A) strong communication skills
B) strong intervention skills
C) strong negotiation skills
D) strong leadership skills

Correct Answer

verifed

verified

When maintaining schedules,if enough _____ and frequent checkpoints exist,problems will be detected rapidly.


A) activity diagrams
B) milestones
C) data flow diagrams
D) viewports

Correct Answer

verifed

verified

Explain the three legs of a project triangle.What makes it challenging?

Correct Answer

verifed

verified

The three legs of a project triangle are...

View Answer

_____ give team members of a project an opportunity to share information,discuss common problems,and explain new techniques.


A) Board meetings
B) Project status meetings
C) Project review reports
D) Status reports

Correct Answer

verifed

verified

A _____ is a review of a project team member's work by other members of a team.


A) critical walk-through
B) foundational walk-through
C) baseline walk-through
D) structured walk-through

Correct Answer

verifed

verified

A Gantt chart can simplify a complex project by combining several activities into a task _____ that contains subsidiary tasks.


A) group
B) hierarchy
C) network
D) bar

Correct Answer

verifed

verified

Briefly explain how project progress is reported and evaluated.

Correct Answer

verifed

verified

Members of the project team regularly re...

View Answer

Tasks are basic units of work that the project manager plans,schedules,and monitors.

Correct Answer

verifed

verified

_____ is a full-featured program that holds the dominant share of the project management software market.


A) Apptivo
B) GanttProject
C) Microsoft Project
D) Gantter

Correct Answer

verifed

verified

GanttProject is a free open-source Java-based project management tool that is available on multiple platforms.

Correct Answer

verifed

verified

The _____ is the most pessimistic outcome of a task.


A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) dominant-case estimate (D)

Correct Answer

verifed

verified

A _____ consists of horizontal bars,connected with arrows that indicate task dependencies.


A) Gantt chart
B) viewport
C) Scatter chart
D) wireframe

Correct Answer

verifed

verified