A) A-B-E-G-H
B) A-C-E-G-H
C) A-D-G-H
D) B-F-H
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.
E) None of the above
Correct Answer
verified
Multiple Choice
A) 2
B) 3
C) 14
D) 16
E) None of the above
Correct Answer
verified
Multiple Choice
A) crashing activities with the lowest overall crash cost
B) crashing activities with the lowest overall normal cost
C) crashing activities on the critical path based on lowest overall cost
D) crashing activities on the critical path based on lowest cost/week
E) crashing activities with the lowest cost/week.
Correct Answer
verified
Multiple Choice
A) a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B) the modal time of a beta distribution.
C) a simple average of the most optimistic, most likely, and most pessimistic times.
D) the square root of the sum of the variances of the activities on the critical path.
E) None of the above
Correct Answer
verified
Multiple Choice
A) 20
B) 22
C) 25
D) 26
E) None of the above
Correct Answer
verified
Multiple Choice
A) normal
B) exponential
C) binomial
D) Poisson
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) 15 days
B) 20 days
C) 17 days
D) 18 days
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 7
B) 16
C) 11
D) 18
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Showing 1 - 20 of 123
Related Exams