Table 12-6 Table 12-6   -Which activities are part of Table 12-6's critical path? A)  A-B-E-G-H B)  A-C-E-G-H C)  A-D-G-H D)  B-F-H E)  None of the above -Which activities are part of Table 12-6's critical path?


A) A-B-E-G-H
B) A-C-E-G-H
C) A-D-G-H
D) B-F-H
E) None of the above

Correct Answer

verifed

verified

D

Given the variability of the activity completion times, the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place.

Correct Answer

verifed

verified

In PERT/CPM, what is meant by the critical path?

Correct Answer

verifed

verified

the series of activities in a ...

View Answer

CPM


A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.
E) None of the above

Correct Answer

verifed

verified

Table 12-5 Table 12-5   -How long could Table 12-5's activity F be delayed without delaying the project? A)  2 B)  3 C)  14 D)  16 E)  None of the above -How long could Table 12-5's activity F be delayed without delaying the project?


A) 2
B) 3
C) 14
D) 16
E) None of the above

Correct Answer

verifed

verified

Reducing the overall activity time is based on which of the following steps?


A) crashing activities with the lowest overall crash cost
B) crashing activities with the lowest overall normal cost
C) crashing activities on the critical path based on lowest overall cost
D) crashing activities on the critical path based on lowest cost/week
E) crashing activities with the lowest cost/week.

Correct Answer

verifed

verified

The expected time in PERT is


A) a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B) the modal time of a beta distribution.
C) a simple average of the most optimistic, most likely, and most pessimistic times.
D) the square root of the sum of the variances of the activities on the critical path.
E) None of the above

Correct Answer

verifed

verified

Figure 12-1 Figure 12-1   -Given the network in Figure 12-1, the time to complete those activities on the critical path is expected to be ________. A)  20 B)  22 C)  25 D)  26 E)  None of the above -Given the network in Figure 12-1, the time to complete those activities on the critical path is expected to be ________.


A) 20
B) 22
C) 25
D) 26
E) None of the above

Correct Answer

verifed

verified

PERT often assumes that time estimates follow which of the following probability distributions?


A) normal
B) exponential
C) binomial
D) Poisson
E) None of the above

Correct Answer

verifed

verified

CPM stands for Comprehensive Project Method.

Correct Answer

verifed

verified

CPM is the acronym for what?

Correct Answer

verifed

verified

Critical P...

View Answer

PERT stands for Probabilistic Evaluation and Review Technique.

Correct Answer

verifed

verified

Consider the project with the following estimates for activity times and precedence relationships: Consider the project with the following estimates for activity times and precedence relationships:   (a) What is the expected duration of the project? (b) What is the project variance? (c) If the deadline of the project is 25 days, what is the probability of finishing the project on time? (a) What is the expected duration of the project? (b) What is the project variance? (c) If the deadline of the project is 25 days, what is the probability of finishing the project on time?

Correct Answer

verifed

verified

(a) 23
(b)...

View Answer

One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.

Correct Answer

verifed

verified

True

The project described by: The project described by:   has a critical path of length of ________. A)  15 days B)  20 days C)  17 days D)  18 days E)  None of the above has a critical path of length of ________.


A) 15 days
B) 20 days
C) 17 days
D) 18 days
E) None of the above

Correct Answer

verifed

verified

In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors.

Correct Answer

verifed

verified

The three time estimates employed in PERT are optimistic time, average time, and pessimistic time.

Correct Answer

verifed

verified

Slack is the time an activity can be delayed without impacting the completion time of the project.

Correct Answer

verifed

verified

Table 12-5 Table 12-5   -How long could Table 12-5's activity E be delayed without delaying the completion of the project? A)  7 B)  16 C)  11 D)  18 E)  None of the above -How long could Table 12-5's activity E be delayed without delaying the completion of the project?


A) 7
B) 16
C) 11
D) 18
E) None of the above

Correct Answer

verifed

verified

C

One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity.

Correct Answer

verifed

verified